Troubleshooting “Little Jake”: Page 2 of 5

Intermediate

Inside this Article

Troubleshooting “Little Jake”
Troubleshooting “Little Jake”
Little Jake needed to come down for repair.
Based on troubleshooting tests, Little Jake needed to come down for repair.
Little Jake’s tail was manually furled out of the wind
Little Jake’s tail was manually furled out of the wind so tower wiring could be checked.
The controller box
The controller box was tested and diagnosed.
Diversion controller, dump loads, and DC panel.
Diversion controller, dump loads, and DC panel.
RE systems’ balance of system (BOS) components
The RE systems’ balance of system (BOS) components, including the charge controller, battery bank, inverters, and DC and AC load power centers.
A megaohmeter (megger)
A megaohmeter (megger) was used to test the THWN conductor insulation.
Yaw slip-ring brushes.
Yaw slip-ring brushes.
Yaw slip rings.
Yaw slip rings.
A high-potential (hipot) tester
Testing for shorts from the conductors to the metal tower was accomplished with a high-potential (hipot) tester.
Testing in the shop
Testing in the shop revealed an internal short—a short from wire to wire—in the armature windings.
Testing in the shop
Testing in the shop revealed an internal short—a short from wire to wire—in the armature windings.
The front end of the generator
The front end of the generator. The blades would be attached to the long shaft.
The rewound armature.
The rewound armature.
Troubleshooting “Little Jake”
Little Jake needed to come down for repair.
Little Jake’s tail was manually furled out of the wind
The controller box
Diversion controller, dump loads, and DC panel.
RE systems’ balance of system (BOS) components
A megaohmeter (megger)
Yaw slip-ring brushes.
Yaw slip rings.
A high-potential (hipot) tester
Testing in the shop
Testing in the shop
The front end of the generator
The rewound armature.

Wiring (from the BOS to the tower and up to the turbine)

  • Conductor continuity, short-circuit, and ground-fault (resistance) tests
  • Splices & terminations

Generator, slip rings & brushes

  • Voltage tests
  • Continuity, short-circuit, and ground-fault (resistance) tests

BOS Checks

Voltage Tests. With the power on, safety gear donned, and all systems enabled, we checked for proper voltage with a multimeter on the battery bank (48 VDC) at the OutBack power center that’s interconnected with two PV systems and the grid (240 VAC), and both the DC and AC sides of the OutBack inverter. We also scrolled through the parameters programmed in the inverter to verify that they matched what was recorded in the MREA operation logs and that nothing had been changed. 

Resistance testing. We then furled the machine and turned off the power from both the grid and the battery bank, since resistance checks cannot—and should not—be done while a system is energized. Still armed with a digital multimeter, now set to ohms, we checked the components in the controller box: fuses, a diode, a circuit breaker, a voltmeter, and an ammeter. The fuses and circuit breakers had continuity, the diode (electrical check-valve) was showing one-way conductivity, and the needles on the analog meters were free to move. The BOS components were verified to be in good working order and not the cause of Little Jake’s problems.

Wiring Checks

Conductor continuity & insulation testing. Next, we tested the underground wiring from the BOS to the junction box at the tower base. We disconnected both ends of the two wires (DC positive and negative) for continuity and insulation tests, using the multimeter to verify low resistance in the copper conductors and a megaohmeter or “megger” to test the THWN conductor insulation. Our megger was very old, with a hand crank and an analog display, but still accurate. Meggers are simple: The operator applies 500 or 1,000 volts to the conductors (in our case, with a hand crank), and the needle should display infinite resistance. Anything else signals insulation breakdown and/or a high-resistance fault. Our conductors passed both the continuity and insulation tests.

It was time to send a crew up the tower to test the wires from the junction box at the tower base to the slip-ring assembly near the tower top. (These were the same tests we just conducted from the BOS to the tower base.) We measured low resistance in the copper wires with a multimeter and saw infinite resistance with the megger. We also checked for short-circuits and insulation breakdown by connecting one test lead of the meter to the metal tower and the other test lead to each of the two power output conductors, one at a time. We were looking for infinite resistance from each conductor to the grounded tower on both the multimeter and the megger, and our tests confirmed that the wiring was good from the BOS to the top of the tower. This meant that our primary suspect was now the wind turbine itself.

Comments (0)

Advertisement

X
You may login with either your assigned username or your e-mail address.
The password field is case sensitive.
Loading